Interior Design Change Order: How to Agree and Price It
· 9 min read
An interior design change order is a short document that states what the client wants to change, what it costs, how it moves the schedule, and that the client approved it before anything is ordered or built. The method has four parts: define the change, price every effect it causes, show the client the difference against the approved estimate, and record the approval. Below is the process, a pricing example and a checklist you can reuse on any project.
What counts as a change and when to stop work
Not every client comment needs a formal document. The rule is simple: if a request changes the approved budget, the approved delivery date, or an item that is already ordered, it needs a change order. Everything else can be handled as a normal revision of a preliminary estimate.
Changes that need a change order
- Replacing an item that the client has already approved.
- Replacing an item that has been ordered, paid or delivered.
- Adding rooms, items or services that are not in the approved estimate.
- Changes to dimensions, finishes or layout after drawings were signed off.
- Any request that pushes delivery or installation dates.
Changes that do not
- Choosing between options that were presented as alternatives before approval.
- Corrections of your own errors, such as a wrong dimension in the estimate. These are handled separately and are usually at the studio's cost.
- Small changes inside an agreed allowance, for example a lamp shade colour within the same price.
The table shows where the cost of a typical change appears, so you do not forget a line when you price it.
| Type of change | Example | Where the cost appears |
|---|---|---|
| Material swap | Porcelain tile replaced with natural stone | Price difference, supplier cancellation fee, contractor rework |
| Added item | Extra wall lights in the corridor | Item price, delivery, installation, electrical work |
| Removed item | Client drops a custom wardrobe | Credit, but possibly a supplier deposit that is not refundable |
| Dimension change | Kitchen island made 20 cm longer | Production change, new measurement, longer lead time |
| Timing change | Client asks for earlier handover | Express delivery, extra labour, possible premium on materials |
The agreement process step by step
The order of steps matters. Most disputes happen because the client approved a idea and not a price, or because the purchase was made before the approval.
- Pause the affected items. Tell the procurement manager and the contractor not to order or install the item until the change is decided. Do this the same day the request arrives.
- Write the request down in the client's words. One or two sentences: what changes, in which room, and why. This protects both sides from a later "I never asked for that".
- Check the current status of every affected item. Not ordered, ordered, paid, in transit or delivered: each status has a different cost of change. Ask the supplier about cancellation terms in writing.
- Price the change completely. Include material, supplier fees, extra work, design time and delay costs (see the next section).
- Estimate the schedule impact. Check which phases depend on this item and how many working days they will move. Say it to the client as a number of days and a new date.
- Show the difference, not the new total. Present the old item, the new item, the net amount and the new delivery date side by side. If it helps the decision, offer a cheaper or faster alternative.
- Get an explicit approval. Approval means a clear "approved" action or a signed document that names the amount and the date. A phrase like "looks nice" in a chat is not approval.
- Update the estimate, budget and timeline, then release the purchase. Only now do you order, and only now the contractor gets the new instruction.
How to price a change
A common mistake is to price only the difference in product price. A change has more layers than that. Go through this list for every request:
- New item at client price. Purchase price plus your usual markup. If you need to check the margin, use the markup calculator.
- Removed item as a credit. Credit it at the client price, not the purchase price, if it can be cancelled.
- Supplier fees. Restocking, cancellation, return shipping, loss of a deposit. Pass these on at cost.
- Extra work on site. Rework, new preparation, repeated visits by the contractor.
- Design and coordination time. New drawings, new selection, extra meetings. Agree on the rate for this in the contract in advance.
- Cost of delay. Storage, repeated delivery, idle crew time, extension of rental.
Worked example with illustrative figures
The client asks to replace the approved bathroom porcelain tile with natural stone. The tile is ordered but not yet shipped. Figures below are an example in EUR, not a benchmark. Studio markup is 20% on products; design time is charged at 80 EUR per hour.
| Line | Basis | Amount, EUR |
|---|---|---|
| New stone, client price | Purchase 2,520 + 20% markup | +3,024 |
| Original tile removed from the estimate | Client price 1,512 (purchase 1,260 + 20%) | -1,512 |
| Supplier restocking fee | Passed on at cost | +189 |
| Extra design time | 4 hours × 80 | +320 |
| Contractor: waterproofing and stone cutting | Quote from contractor | +450 |
| Storage during the delay | Estimate | +120 |
| Net change | +2,591 |
Schedule impact in the same example: stone has a longer delivery time, so the bathroom finishing phase moves by 10 working days. The client sees one number, +2,591 EUR, and one date, but you keep every line behind it.
Keep the margin visible to yourself only
The client needs the net amount and the reason for it. Purchase prices and markup stay in your internal view. If a change makes the margin on the project fall, you will see it at the moment of the request and not at the end of the project.
What a change order should contain
A change order does not have to be long. One page is enough if it answers the questions below. Use this as a checklist before you send it:
- Project name, room and the date of the request.
- Short description of the change in the client's words.
- The original item and the new item with photos, SKU and dimensions.
- Itemised cost: additions, credits, fees, work and time.
- Net amount and the currency.
- Effect on the delivery date and on the dependent phases of the schedule.
- Payment terms for the extra amount: advance, balance, due date.
- The deadline for the decision, with the reason (for example, the supplier holds the price for 5 working days).
- Name of the person who approves and the date of approval.
- Link to the updated estimate.
Set a decision deadline
An open change blocks purchasing. State the last date on which the client can decide without moving the schedule, and say what happens after it: the original item goes ahead, or the dates move.
Mistakes to avoid
- Ordering before the approval because "the client will surely agree".
- Agreeing by phone and writing nothing down.
- Pricing the product difference only and forgetting fees, work and time.
- Not telling the client how the change moves the handover date.
- Mixing the change with a normal revision, so that the client does not know which requests are paid.
For schedule effects, it helps to look at the whole chain of ordering, delivery and installation, not at one item. The procurement timeline shows which dependent phases move when one item changes.
How to do it in ArchiBoard
The client portal lets the client review items and approve or reject them without registering. The projects chapter of the help center explains the project structure in more detail. A change order workflow looks like this:
- Open the project, go to Estimates and find the item the client wants to change. Open Item details and click Add analog to add the proposed replacement by URL, from the wishlist or from the catalog. It appears as a branch under the main item.
- Check the item's status. Click the status and use Change Status to add a comment and attachment, such as the supplier's reply about cancellation terms.
- In Vendor & payment, check what has been paid and what the delivery dates are. Switch the estimate to Economics mode to see how the change affects markup and profit. Switch back to Specification for the client view.
- Tick the affected rows and click Export to PDF. Enable Only selected items and include alternatives, then click Download PDF. The document shows the alternative under the main item with the label "Alternative option", and the base total and the total with alternatives. Your purchase price, markup and profit are not included.
- Open Client portal → Link access and create a link with the permission View + approve / reject. Use Client preview to check what the client sees, and tick the items under "What the client sees in the item card", for example "Price" and "Question button". The client can approve, reject or ask a question, and the question reaches the responsible person as a task.
- After the decision, set the status in the estimate and update the plan in Timeline. Dependent phases shift automatically when you move a linked phase, and the Upcoming purchases block shows what to order first. In Project Finances, a warning appears if the estimate exceeds the approved budget.
- Upload the signed document or the confirmation to Files → "Contracts & client documents". The Activity Feed keeps the history of price and status changes.
The
FAQ
Should every small change get a formal change order?
No. Use a formal document when a change affects the approved budget, the delivery date or an item that is already ordered. For small adjustments inside an agreed allowance, a short written confirmation to the client is enough. The point is to be able to show later what was agreed.
Who pays when the change comes from my own mistake?
If the error is the studio's, such as a wrong dimension in the estimate, the studio normally covers the cost and does not issue a change order. Record it in the project history anyway. Separate such corrections clearly from client requests, so the client sees the difference between a paid change and a fix.
What if the client approves only verbally?
Confirm it in writing at once: send a short message with the amount, the new date and a request to reply "approved". Do not order until you have it. A verbal agreement is hard to prove if the client later disputes the cost or the delay.
Can I charge for design time on a change?
Yes, if the contract or the first estimate says that changes after approval are charged at an hourly rate or as a fixed fee. Tell the client about this before the project starts. Charging for time without prior agreement usually causes disputes, even when the time was really spent.
What should I do if the item has already been delivered?
Check the supplier's return conditions first. Then price the return shipping, any restocking fee, the cost of keeping the item and the new purchase. If the return is not possible, offer the client a choice: keep the item, resell it, or use it in another room. Write down the decision in the change order.