BOQ for Interior Design: Format, Columns and Free Template

· 8 min read

A BOQ for interior design is an itemised list of every piece of work and supply on a project, with a description, unit, quantity, rate and amount for each line. A good one is grouped by room or trade, has measurable descriptions, and keeps the client-facing columns separate from your internal cost columns. Below is the structure, the columns, a worked example and a checklist you can rebuild in Excel or Google Sheets.

What a BOQ must do on an interior project

On a typical Mumbai or Bengaluru apartment, the work is split between local carpentry and civil teams and imported or branded items such as lighting, sanitaryware and hardware. A BOQ has to hold both in one document. It does three jobs:

  • Prices the scope. The client sees what they are paying for, line by line.
  • Fixes the scope. Vendors and contractors quote against the same lines, so quotes can be compared.
  • Drives procurement. Each line should tell you what to order, from whom and by when.

A BOQ is not the same as a specification. The BOQ says how much; the specification says exactly what (material, finish, make, model). In small studios both often live in one sheet, which is fine as long as the description column is precise.

Group by room or by trade

Grouping by trade (civil, false ceiling, electrical, carpentry, painting, flooring, loose furniture, lighting) is easiest for contractors and vendors. Grouping by room (living, kitchen, master bedroom) is easiest for clients and for budget control. Pick one as the primary grouping and add the other as a column, so you can filter either way.

Columns to include in the BOQ

Keep the client version short and the internal version complete. The table below is a workable layout.

ColumnWhat goes in itClient copy
Item no.Running number or code by trade (for example, CPT-01 for carpentry)Yes
Room / areaLocation of the itemYes
DescriptionMaterial, finish, size, make or model, scope (supply only or supply and install)Yes
Unitsq ft, sq m, rft, nos, set, lump sum. Use one system consistentlyYes
QuantityNet quantity plus wastage or reserve, in whole packs where relevantYes
RatePrice per unit charged to the clientYes
AmountQuantity × rateYes
VendorWho supplies or executesNo
Purchase rateWhat you pay the vendorNo
Markup / marginYour percentage and rupee amountNo
Lead time and order-by dateWorking back from the site dateNo
StatusPending approval, approved, ordered, delivered, installedOptional
RemarksExclusions, assumptions, alternatesYes

A worked example

These numbers are illustrative only. Say a bedroom wardrobe is 8 ft wide and 7 ft high, so the area is 56 sq ft. If your example rate is ₹1,800 per sq ft, the amount is ₹1,00,800. The description should still say what that rate includes: carcass material, shutter finish, hardware, internal fittings, and whether the loft is counted separately.

How to build the BOQ, step by step

  1. Freeze the scope list first. Walk through the drawings room by room and list every work item and every loose item. Do not type rates yet. A missing line costs you later; an extra line is easy to delete.
  2. Write measurable descriptions. "Wardrobe" is not a BOQ line. "Full-height wardrobe, 8 ft × 7 ft, laminate shutters, soft-close hinges, 2 internal drawers, supply and install" is. If two vendors could read a line differently, it is too vague.
  3. Take quantities from drawings, then verify on site. Measure net areas from plans, then check on site after civil work. For finishes, add a reserve for cutting and breakage. For example, if you need 100 sq ft of tile with a 10% reserve, you buy for 110 sq ft. If one box covers 12 sq ft, that is 10 boxes, not 9.2.
  4. Convert to whole packs. Tiles, wallpaper and flooring are sold in boxes or rolls. Show the purchase quantity in whole packs and keep the net quantity in the remarks or a hidden column.
  5. Collect vendor quotes against the same lines. Send the same line list to each vendor. Record the purchase rate, what it includes (delivery, installation, unloading) and its validity.
  6. Add your margin. Decide whether you earn through markup, commission or a share of the vendor discount, and apply it consistently. The markup calculator helps check the arithmetic between purchase price, markup and client price.
  7. Add provisional sums, alternates and exclusions. If an item is not yet selected (a chandelier, say), put a provisional allowance and mark it clearly. Put alternates on separate lines so the client can compare. List what is not included, such as appliances, curtains or approvals.
  8. Handle tax and terms separately. Whether rates are shown with or without GST, and how taxes appear on your invoices, is a question for your CA. Contract terms, payment milestones and variation clauses belong in your agreement and should be checked with your CA or legal adviser, not improvised in the BOQ.

Procurement columns that save you later

The columns that most BOQs miss are the ones that decide whether the site runs on time. Imported lighting or fittings may take many weeks, while local carpentry may be ready in a few. For example, with an 8-week lead time on a light fitting and a false ceiling due on site in week 10, your order-by date is already tight. If it only lives in someone's head, it gets missed.

  • Lead time in weeks, as quoted by the vendor and noted with the date of the quote
  • Order-by date, calculated backwards from the date the item is needed on site
  • Advance paid and balance due, per vendor
  • Planned and actual delivery date, so you can see which vendors reschedule often
  • Acceptance status on site: quantity, size, colour and SKU checked against the line

Checklist before you send the BOQ to the client

  • Every line has a unit, quantity, rate and amount, and the totals add up
  • Descriptions state supply only or supply and install
  • Quantities include reserve, rounded to whole packs where needed
  • Purchase rates, markup and profit columns are hidden or removed from the client copy
  • Provisional items, alternates and exclusions are marked
  • Lines for items without a price yet say "price on request", not zero
  • Version number and date are on the sheet, so you know which BOQ the client approved
  • Tax treatment has been confirmed with your CA

How to do it in ArchiBoard

If your BOQ already lives in Excel or Google Sheets, you do not have to retype it. You can also start from the free estimate template and move it into a project when it is ready. For India-specific setup, see ArchiBoard for India.

  1. Open Home → "New Project", enter the name and city, and choose your studio's role.
  2. Go to Estimates → "Import". Upload an Excel, CSV or PDF file, or paste a Google Sheets link (the sheet must be accessible via the link).
  3. Check what each column means (name, quantity, price and so on). The system usually detects this automatically.
  4. Choose a room to import into, or keep the breakdown from the file, then click "Import". Sections like "Kitchen" and "Bedroom" become project rooms. If you make a mistake, use Activity Feed → "Undo import".
  5. To add a product from a store's website, click "Add item", paste the link and click "Auto-fill". Check the fields and click "Save item".
  6. Switch the estimate to "Economics" mode to see purchase price, markup and profit per line. "Specification" mode shows what and how much, without internal finances.
  7. For the client, click "Export to PDF", select the rooms you need under "Rooms", then click "Download PDF". Purchase price, markup and profit are not included in the client PDF.

Read more about how estimates work. The Free plan allows up to 20 items, so a full-home BOQ will normally need Pro.

Questions and answers

What is the difference between a BOQ and an estimate?

In everyday studio practice the two terms overlap. A BOQ stresses quantities and units against which vendors quote, while an estimate stresses the cost to the client. Many designers use one sheet for both: the BOQ lines with quantities, plus rate and amount columns. What matters is that every line is measurable and priced.

Should the client see my purchase rates and margin?

Usually not. Prepare a client copy with description, unit, quantity, rate and amount, and keep purchase rate, markup and profit in an internal version. How you disclose commissions or vendor discounts is a matter between you and your client, and it should be covered in your agreement. Check wording with your CA or legal adviser.

Should I organise the BOQ by room or by trade?

Either works if the other is available as a filter. Trade grouping suits contractors who quote by scope, while room grouping suits clients who think in terms of the kitchen or bedroom budget. Add a room column and a trade or category column, then sort whichever way the audience needs.

How do I handle items that are not selected yet?

Keep the line in the BOQ with a provisional allowance and mark it clearly, or show "price on request" if you have no number. Do not leave it blank, because the total will look complete when it is not. When the client chooses, replace the allowance with the actual item and record the change with a date.

How much wastage or reserve should I add?

It depends on the material, the layout and the installer, so there is no single right figure. Ask your installer or vendor for their recommended reserve, apply it as a percentage to the net quantity, and round up to whole boxes or rolls. Record the reserve percentage in the sheet so the logic is visible.