How to Prepare a BOQ for an Interior Project in India

· 9 min read

To prepare a BOQ for an interior project, freeze the drawings, split the scope by room and trade, calculate net quantities with wastage, write one clear specification per line, and attach a rate and a vendor to each line. The result is a priced list the client can approve and procurement can order from. This guide shows the process as it works on a typical fit-out in Mumbai, Bengaluru or Delhi NCR, where local carpentry and imported lighting or fittings often sit in the same document.

What a BOQ for an interior project should contain

A BOQ (bill of quantities) is more than a price list. It is the single reference that links drawings, budget and purchasing. If a line cannot be traced to a drawing tag, a room and a vendor, it will cause an argument later, at the site or at the invoice stage.

Use the same columns on every project. A ready estimate template can save the first hour, but the columns below are what matter.

ColumnWhat goes inWhy it matters
Item codeA tag that matches the drawing, for example LT-01 for a pendantTies each line to the drawing set
Room / areaLiving, master bedroom, kitchenGives a budget per room
Description and specMaterial, finish, size, colour, model or SKUPrevents silent substitutions
Unit and quantityNos, sq ft, running ft, lump sumMakes the amount checkable
Wastage / reservePercentage or extra packsCovers cutting and breakage
Rate and amount₹ per unit, supply and installation shown separatelyShows what is bought and what is labour
VendorWho supplies the lineLets you group orders and payments
Lead timeWeeks from order to siteSets the order-by date
RemarksExclusions, options, approvalsRecords assumptions

Step by step: building the BOQ

  1. Freeze the drawing version. Note the drawing set and revision the BOQ is based on. Every later change becomes a revision of the BOQ, not a silent edit.
  2. Split the scope by room and trade. Typical trades are civil and demolition, false ceiling, electrical, plumbing, flooring, wall finishes, carpentry, lighting, sanitary fittings, furniture and soft furnishings, and services. Rooms come first, trades second. This lets you see the budget per room and per vendor from the same list.
  3. Take net quantities from the drawings. Measure each room's floor, wall, ceiling and joinery. Deduct openings only by a rule you have agreed with the contractor and write that rule in the remarks.
  4. Add wastage and convert to purchasable units. Tiles, wallpaper and flooring are sold in boxes or rolls, not square feet. Add a reserve for cutting, then round up to whole packs. For example, if you need 410 sq ft net with a 10% reserve and a box covers 16 sq ft, you order 451 sq ft, which is 28.2 boxes, so 29 boxes. The reserve percentage is your call. Confirm it with the installer and the vendor.
  5. Write one specification per line. Include material, finish, dimensions, colour and the reference product. "Wardrobe, laminate" is not a specification. "Wardrobe, 2400 × 600 × 2400 mm, laminate shutters, soft-close hinges" is.
  6. Collect rates from quotes. Use written quotes from vendors and carpenters, not memory of the last project. Note the quote date and the validity period.
  7. Mark optional, provisional and excluded items. Do not bury them. Optional items stay out of the total. Provisional sums are labelled as such, and exclusions are written in plain words.
  8. Review with the site team, then version it. Ask the site supervisor to check the quantities for anything that looks wrong on the ground. Save the result as revision 1.

Supply only, install only, or both

Decide for each line whether the rate covers supply, installation or both, and show it in the description. Imported lights are usually supplied by one vendor and installed by your electrician. Local carpentry is usually supplied and installed by one party. If the BOQ mixes these without saying so, installation gets counted twice or not at all.

Quantities, units and wastage

Unit confusion is the most common source of wrong BOQ totals. Agree the measurement method before pricing, and write it in the remarks.

Item typeTypical unitWhat to check
Floor tiles, stone, wood flooringSq ft or sq m, then boxesReserve for cuts, pattern direction, box coverage
Paint, wallpaper, panelsSq ft, rolls or panelsOpening deduction rule, roll coverage, number of coats
Wardrobes, kitchen, built-in unitsSq ft of surface, running ft or per unitMeasurement method, hardware, internal finish, countertop
False ceilingSq ftDrops, coves and light pockets as separate lines
LightingNosDrivers, tracks, dimmers and controls as their own lines
Sanitaryware and fittingsNosWhether trims, concealed bodies or accessories are included
Furniture and soft furnishingsNos, metres of fabricDimensions, fabric and finish, lead time
Labour, supervision, transportLump sum or daysWhat exactly is covered

When one product serves several rooms, such as the same tile in a bedroom and a passage, keep it as one purchase with a quantity split per room. You then see room budgets correctly and still order and pay once.

Imported items, markup and exclusions

The lines that move your budget are usually the imported ones: lighting, sanitary fittings, special hardware, some furniture. Show the vendor's price in the quoted currency along with the date of the quote. For duties, GST and customs treatment, check with your CA or customs broker and do not guess them into a rate. Put a lead time on every imported line, because it decides when the project can hand over.

Markup belongs in your internal view, not in the client's BOQ. Work out how much you add on each line, or on each group of lines, before the client version is exported. The markup calculator helps check the arithmetic: purchase price, markup and client price.

Checklist before sending the BOQ to the client

  • Drawing set and revision are written on the first page.
  • Every line has a room, a unit, a quantity and a rate.
  • Wastage is applied and packs are rounded up where the item is sold in packs.
  • Supply, installation or both is stated for each line.
  • Imported items show the quote date, currency and lead time.
  • Optional and provisional items are labelled and kept out of the firm total.
  • Exclusions are listed in plain words.
  • Tax treatment is confirmed with your CA, not assumed.
  • Vendor quotes are attached or referenced, with validity dates.
  • Internal purchase prices and markup are removed from the client copy.

How to do it in ArchiBoard

The same method works in ArchiBoard estimates. See also the ArchiBoard page for India for the local workflow.

  1. On the home page click "New Project", then enter a name, the city and your studio's role.
  2. Open the project and go to "Rooms" → "Add room" for each room. Each room has its own estimate and shows "Budgeted", "Left" or "Over budget".
  3. If you already have a BOQ in Excel, CSV, PDF or Google Sheets, go to Estimates → "Import". Upload the file or paste the sheet link, check what each column means, choose a room or keep the file's breakdown, then click "Import". Sections like "Kitchen" become rooms. If it goes wrong, use "Undo import" in the Activity Feed.
  4. To add a product from a store page, click "Add item", paste the link and click "Auto-fill". Check the fields and click "Save item". For one product used in several rooms, turn on "In several rooms" and choose "Evenly", "By quantity" or "By percent".
  5. In the item card enter the net quantity, the reserve in percent and "Pieces per package" or "m² per package". The "Qty" column then shows how much to buy in whole packages.
  6. Switch the estimate view to "Economics" to work with supplier discount, markup and profit. Switch to "Specification" to see what the client sees.
  7. In the item row open "Vendor & payment" to choose the vendor, add invoices and set planned delivery dates. Use "By order priority" to see what has to be ordered first, and the "Upcoming purchases" block in "Timeline".
  8. To send the client a version, click "Export to PDF", choose the rooms, turn prices and photos on or off, then click "Download PDF". Purchase price, markup and profit are not included in the client PDF. To show a cheaper option, add it with "Add analog" and include alternatives in the export.

The Free plan allows up to 20 items, so a full fit-out BOQ will need Pro. From India you pay by card in EUR through Lemon Squeezy in "Settings → Billing", and your bank converts the amount to INR.

Questions and answers

What is the difference between a BOQ and an estimate?

A BOQ lists every item with its specification, unit and quantity, so that anyone can price it the same way. An estimate adds rates, markup and totals. In daily interior work the two are usually one document: the BOQ is the quantity and specification layer, and the estimate is the same list with prices.

How much wastage should I add?

It depends on the material, the room shape and the installer. Large-format tiles in a room with many corners need more reserve than a plain rectangular floor. Treat any percentage as a working assumption, for example 10%, and confirm it with the vendor and the installer before you order. Write the percentage you used in the BOQ.

Should the BOQ include GST?

Show tax in the way your contract and invoicing require, and keep it consistent across all lines. Tax treatment differs by item and by how the work is billed, so check with your CA before you finalise the client BOQ. Do not hide a guessed tax rate inside unit rates.

Can I turn an existing Excel sheet into a BOQ?

Yes. First clean the sheet: one row per item, a clear unit and quantity, and a room or section name. Then import it and check the column mapping. Add the missing items afterwards: lead time, vendor, reserve and specification. A sheet that already follows the column table above will import with the least rework.

How often should I revise the BOQ?

Revise it whenever the drawings change, the client approves or rejects an item, or a vendor quote expires. Keep earlier versions so you can show what changed and why. Small price updates can wait for the next revision, but quantity or specification changes should be recorded immediately.