Interior Design Handover Checklist: Before the Client Moves In

· 9 min read

An interior design handover checklist is a fixed list of checks you run room by room before the client takes the keys: every item has arrived, matches the specification, works, is installed correctly and is documented. The aim is to find defects while contractors and suppliers are still engaged on the project, not after the family has moved in. Below is the process in five parts: preparation, a room-by-room walk, reconciliation with the estimate, a snag list, and the final handover package.

Prepare the handover two weeks before the walk

Most handover problems start earlier: a late delivery, an unconfirmed installation slot, or no reference list to check against. Do the preparation while there is still time to fix things.

  1. Fix the reference list. Take the current approved estimate, grouped by room. This is what the client paid for, and every check on the walk is made against it.
  2. Review item statuses. Separate items that are delivered, accepted and installed from those that are still ordered or in transit. Anything not on site two weeks before the walk needs a confirmed date from the supplier.
  3. Chase missing items. For each late item, get a written new delivery date and record the reason. If the date is after the planned move-in, tell the client now, not on the day.
  4. Book the people. Contractor foreman, installers of built-in furniture and appliances, and a cleaning crew for the day before the walk.
  5. Choose the time. Walk in daylight with all lights, water and heating on. Evening walks hide wall and paint defects.
  6. Pack the tools. Tape measure, torch, small level, socket tester, phone charger, masking tape or sticky dots for marking defects, and a camera or phone.

Who attends the internal walk

PersonWhy they are needed
Lead designerJudges whether the result matches the design intent
Procurement managerCompares delivered items with the estimate and the supplier documents
Contractor foremanTakes responsibility for construction defects and gives fix dates
Installer or supplier representativeNeeded for complex items: kitchens, built-in wardrobes, windows, appliances

Do this internal walk first, without the client. Fix what you can before the client sees the space.

Walk the site room by room

Use the same route every time

Go in a fixed order: entrance, living areas, kitchen, bedrooms, bathrooms, technical rooms, balcony or terrace. A fixed route means you do not skip a storage room because it was not in the renders. Finish one room completely before moving on, and record defects while you are standing in that room.

Test the room, do not just look at it

A room can look finished and still fail in use. Open, switch on and run everything.

  • Walls and ceilings: check paint evenness with a torch held at a low angle, plus joints, corners, cracks and stains.
  • Floors: look for gaps, squeaks, scratches, uneven transitions between materials and loose skirting.
  • Doors and windows: open and close each one, check locks, handles, gaps and sealing, and that protective film is removed.
  • Electrics: test every socket and switch, and run every lighting scene. Confirm that panel labels match the real circuits.
  • Plumbing: run every tap, flush every toilet, fill and empty sinks and baths, and check under sinks for leaks after ten minutes.
  • Heating, ventilation, air conditioning: switch each on, listen for noise, and check that air actually moves.
  • Furniture: open every drawer and door, check alignment, hinges, soft-close, levelling and fixings to the wall.
  • Soft furnishings: check curtain length, rail operation, and that rugs and upholstery are the specified fabric.
  • Appliances: power on, run a short programme, and check that the model matches the specification.
  • Cleanliness: no dust on surfaces, no glue or paint on glass and hardware, no packaging left behind.

Reconcile delivered items with the estimate

The walk checks the work. Reconciliation checks the goods. Go through the estimate one room at a time and compare each line with what stands in the room.

AttributeCompare againstTypical finding
Model or SKULabel on the product and the supplier documentA similar model was substituted without approval
Colour and finishApproved sample or specificationDifferent batch or tone, visible next to other items
DimensionsEstimate and drawingItem is a few centimetres off and does not fit the niche
QuantityEstimate line and packing listA set is short by one piece
ConditionVisual check, all sidesChips, scratches, transport damage under packaging
PositionPlan or layoutItem installed in the wrong place or orientation

Example: the estimate shows 12 dining chairs at 180 EUR each. The room has 11 and a damaged leg on one of them. That is two separate findings: a quantity shortfall (1 chair, 180 EUR) and a condition defect. Each needs its own claim to the supplier, with its own photo and date.

Do not forget items that are easy to lose: spare tiles, extra handles, installation hardware, remote controls, keys for built-in furniture.

Build a snag list the contractor can act on

A vague note such as "bathroom needs work" cannot be fixed or closed. Write each defect as a separate entry with a place, a photo, an owner and a date.

What every entry must contain

  • Room and exact location (for example, "bedroom, wall behind the bed, left of the socket").
  • One photo with context and one close-up.
  • What is wrong and what the correct result should be.
  • Responsible party: contractor, supplier, installer or studio.
  • A fix date, and a way to confirm that it is fixed.

Sort by severity

SeverityExampleActionExample deadline
Blocks move-inWater leak, non-working socket circuit, unsafe fixingFix before the client enters1-2 days
Affects daily useDrawer that does not close, missing shelf, appliance not connectedFix or agree a date at handover3-7 days
CosmeticPaint touch-up, small scratch, sealant lineFix after move-in by appointment2-3 weeks
Waiting for goodsReplacement item on order, missing partConfirm supplier date, give client a temporary solutionPer supplier date

The deadlines above are an example only. Set real ones with the contractor and write them into the list.

Hand over the documents and run the client meeting

The client should leave the handover with everything needed to live in and maintain the space. Prepare this package before the meeting.

  • Keys, remotes, access codes and the places where spare keys are kept.
  • Manuals and warranty cards for appliances, plumbing fixtures, lighting and smart-home equipment.
  • Care instructions for sensitive materials: natural stone, oiled wood, upholstery, special paint.
  • Spare materials and their codes: paint colours, tile batch, wallpaper roll numbers.
  • Supplier and contractor contacts for warranty questions.
  • A final list of purchased items by room, so the client knows what they own.
  • Marked electrical panel and water shut-off points.
  • The agreed snag list with owners and dates.

Warranty periods and obligations depend on your contract and local rules. Use the terms you agreed, and do not promise more in conversation than is written down.

Run the meeting in this order

  1. Walk the space with the client in the same fixed route.
  2. Show how things work: heating, lighting scenes, appliances, shut-off valves, window and door adjustments.
  3. Show the open snag items openly, with the dates for each.
  4. Ask the client to add anything you missed, and record it in the same format.
  5. Agree a follow-up visit to close the remaining items.
  6. Send the written list to the client the same day.

How to do it in ArchiBoard

If the estimate, delivery dates and tasks already live in one project, the checks above become a short sequence of actions. The procurement timeline shows what is late, and tasks carry the snag list.

  1. Open the project, go to Estimates and use Group by → "By room". Use Filter by status to list items that are not yet "Delivered", "Accepted" or "Installed".
  2. Open Timeline and check the "Upcoming purchases" block and the waiting bars. For an overdue delivery the system creates the task "Request new delivery date". Record changed dates in Vendor & payment with a "Reason for rescheduling".
  3. For each delivered item, click Acceptance in the row. In the "Inspection" section check SKU, colour, dimensions and quantity, attach "Delivery notes" and "Photo report", and choose "Accepted" or "Discrepancy". Write a comment you can reuse in a supplier claim.
  4. Use "AI label check": photograph the product label and the system compares the codes and EAN with the estimate item.
  5. For defects, tick the affected rows and click Create task. Pick a template such as "Find analog" or enter your own name, and set the deadline by date or in working days. Tasks go to the responsible people from the project settings.
  6. In Timeline, switch "Mode" to "Board" to track snag tasks by status.
  7. Acceptance photos are saved in Files → "Acceptance photos". To send the client a list, use Export to PDF, select the rooms, enable "Only selected items" and press "Download PDF". Details are in the export chapter.

FAQ

When should the handover walk happen?

Hold the internal walk two to three days before the client meeting. That gives contractors time to fix blocking defects and cleaners time to finish. Schedule the client meeting only after the blocking items are closed, and keep a buffer for one more fix cycle.

Who should attend the handover with the client?

The lead designer and the person who knows the purchases best, usually the procurement manager. Bring the contractor foreman if technical questions are likely. Keep the group small: the client should be able to ask questions and look around without a crowd of people.

Can the client move in while some defects are open?

Yes, if nothing blocks safe daily use and the open items are cosmetic or wait for goods. Put each one in writing with an owner and a date. Defects that affect safety, water, electricity or the use of a bathroom or kitchen should be closed before move-in.

How do I document a defect so a supplier accepts the claim?

Record the item, SKU, date of delivery, a photo of the label, a photo of the damage in context and a close-up, and a short description of the problem. Attach the delivery note. Send it quickly: the longer the gap between delivery and claim, the easier it is to dispute.

How long does a handover walk take?

It depends on the size and the number of items. As a rough guide, allow about an hour for a small apartment and a half day or more for a large house. The internal walk takes longer than the client meeting, because testing every item is slow and cannot be rushed.