Kitchen Procurement Checklist: Appliances to Fittings
· 8 min read
A kitchen procurement checklist is a list of every appliance, worktop, sink, tap and fitting, with the data needed to order each one and the order in which the decisions must be made. The order matters more than the list itself: appliances fix the cabinet and cut-out sizes, and the sink and hob fix how the worktop is fabricated. If one of them changes late, other orders have to be redone. The method below puts the dependencies first and the shopping second.
Fix the order of decisions before you order anything
Most kitchen delays come from decisions made in the wrong sequence, not from slow suppliers. A worktop cannot be cut until the sink and hob are final. Cabinets cannot be finished until the appliance sizes are confirmed. Work through the kitchen in this order:
- Freeze the layout, ceiling height and wall dimensions, including the positions of water, drain, sockets and ventilation.
- Choose all appliances with exact model numbers, including the extractor hood.
- Choose the sink, tap and hob models, because these set the worktop cut-outs.
- Send the appliance data sheets to the kitchen maker and get the cabinet drawings confirmed.
- Order the worktop only after the cabinets are installed and the site is measured.
- Order fittings and small parts together with the cabinets, so they arrive in one delivery.
What blocks what
| Item | Must be known before ordering | What it blocks |
|---|---|---|
| Built-in appliances | Exact model, niche size, connection type | Cabinet drawings, worktop cut-outs |
| Hob | Model, cut-out size, minimum distance to walls | Worktop fabrication, hood position |
| Sink | Model, mounting type, bowl position, cut-out template | Worktop fabrication, base cabinet size |
| Tap | Model, hole diameter, height, spout reach | Worktop drilling, sink compatibility |
| Worktop | Final cabinets, sink, hob, edge profile, upstand | Installation of the sink, hob and tap |
| Handles and hinges | Door and drawer sizes, hole spacing | Cabinet finishing |
Appliances: specify them before the cabinets are made
Specify appliances first, because the cabinets are built around them. Each appliance needs a complete data record, not just a name and a price. Dimensions in a catalogue headline are often outer sizes, while the kitchen maker needs the niche size and the ventilation gaps.
Data to collect for every appliance
- Exact model name and SKU, with a link to the manufacturer's data sheet.
- Outer dimensions and the required niche dimensions (width, height, depth).
- Door hinge side and whether the door can be reversed.
- Panel-ready or visible front, and the front weight if a cabinet panel is attached.
- Electrical load, plug type and the socket position behind or beside the unit.
- Water inlet and drain position for the dishwasher, the washing machine and the coffee machine with a water supply.
- Ventilation gaps, minimum distances to walls and to combustible surfaces.
- Extractor: duct diameter, duct route, recirculating or external, and the air flow needed for the hob.
- Delivery time, packaging size and whether the supplier delivers to the floor of the apartment.
Conflicts to check on paper
Before the data goes to the kitchen maker, check these combinations on the drawing: oven below the hob needs a compatible cut-out depth; a tall fridge column needs the door to open past the adjacent wall; a hood needs enough height above the hob; a dishwasher needs a drain within the hose reach. A short call with the kitchen maker at this stage costs less than a replacement cabinet.
Worktops, sinks and taps: the dependency chain
The worktop is the item with the most dependencies and the least tolerance for change. Once it is cut, a different sink or hob usually means a new slab. Follow this chain:
- Confirm the sink, hob and tap models in writing with the client.
- Get the cut-out templates or technical drawings from the manufacturers and pass them to the worktop fabricator.
- Wait until the base cabinets are installed and levelled. Measure on site, not from the drawing.
- Agree the edge profile, the upstand or splashback, the joint positions and the direction of the pattern if the material has one.
- Approve the fabricator's shop drawing with all cut-outs and tap holes marked.
- After installation, connect the sink, tap and hob. Plumbing and electrical connections come last.
Sink and tap compatibility checks
- Mounting type: top-mounted, flush or undermount. The last two need fabrication work on the worktop edge, and the fabricator must confirm that the material allows it.
- Bowl and drainer position against the base cabinet width and the plumbing outlet.
- Number and diameter of tap holes, and the thickness of the worktop at the sink.
- Tap height against the wall cabinet or the window sill, and spout reach over the bowl.
- Waste kit, overflow type, waste disposer if planned, and the siphon space in the cabinet.
- Water filter or hot water tap: extra holes, extra under-sink space, extra power supply.
Fittings and small parts: what gets forgotten
Small parts are cheap but stop the installation when they are missing. Treat them as real estimate items with their own supplier, price and delivery date, not as a line called "miscellaneous".
| Group | Examples | Order together with |
|---|---|---|
| Cabinet hardware | Handles, hinges, drawer runners, soft-close dampers, push-to-open | Cabinets |
| Interior organisers | Cutlery trays, pull-out bins, corner mechanisms, plinth | Cabinets |
| Plumbing parts | Waste kit, siphon, flexible hoses, angle valves, filter | Sink and tap |
| Electrical parts | Sockets, switches, under-cabinet lighting, drivers, cable channels | Electrical phase of the works |
| Installation materials | Sealant, fixings, joint filler, edge strips, levelling feet | Worktop and appliances |
Final check before the last order
- Every appliance, sink and tap has a model number and a confirmed price.
- Every cut-out has a drawing that matches the final model.
- Handle hole spacing matches the door drilling on the cabinet drawings.
- Each plumbing and electrical connection has its part on the list.
- The client has approved the visible items: handles, tap finish, worktop sample, sink colour.
Work back from installation and control delivery
Once the sequence is clear, convert it to dates. Start from the day the worktop or the appliances must be installed and subtract each step. The numbers below are an example only; replace them with the lead times your suppliers confirm in writing.
| Step (example) | Example duration | Counted back from installation day |
|---|---|---|
| Worktop installed | 1 day | Day 0 |
| Worktop fabrication | 10 working days | Day -10 |
| Site measurement and shop drawing approval | 5 working days | Day -15 |
| Cabinets installed and levelled | 3 working days | Day -18 |
| Appliances on site, checked | Before cabinet installation | Day -20 or earlier |
Add a buffer on top of each supplier date. If a supplier moves a delivery, record the new date and the reason, so you can see later which suppliers reschedule often.
Checks on delivery
- Compare SKU, colour, dimensions and quantity with the estimate line before signing the delivery note.
- Open the packaging of appliances and worktop pieces in front of the courier when possible, and photograph any damage.
- Write the result per item: accepted or discrepancy, with a comment you can use in a claim.
- Store accepted appliances protected and unplugged until the cabinets are ready.
How to do it in ArchiBoard
The steps above map onto the kitchen estimate and the project timeline. See the procurement timeline feature for the overview.
- Open the project, go to "Rooms" → "Add room" and create "Kitchen". The room shows "Budgeted", "Left" or "Over budget".
- Go to Estimates → "Add item", paste the product link and click "Auto-fill". Check dimensions, SKU and delivery time, then click "Save item". You can also save products from a store page with the web clipper (Chrome only).
- Add niche sizes, cut-out notes and hinge side to the item description. To offer a cheaper or faster model, open "Item details" → "Add analog".
- Switch the estimate to "By order priority" to see what to order first. The "Upcoming purchases" block on the Timeline shows the same by order deadline.
- In the item row open "Vendor & payment": choose the supplier, set "Supplier payment" and enter planned delivery dates. If a date moves, select a "Reason for rescheduling".
- Check the kitchen rows with checkboxes and click "Create task". Templates such as "Approve item" and "Clarify delivery dates" create one task per item. More in the help chapter on tasks.
- When goods arrive, click "Acceptance" in the item row, check SKU, colour, dimensions and quantity, attach a "Photo report" and set "Accepted" or "Discrepancy".
FAQ
What should I order first in a kitchen project?
Order or at least finally select the appliances first, because they define the cabinet drawings and the worktop cut-outs. Items with the longest lead time, often built-in appliances and custom cabinets, should be placed as soon as the model data is confirmed. The worktop is ordered last of the big items, after site measurement.
When can the worktop be ordered?
Order it after the base cabinets are installed and levelled, and after the sink, hob and tap models are final. The fabricator measures on site and issues a shop drawing. Ordering from the design drawing alone risks a mismatch of a few millimetres, which can be expensive on stone or composite slabs.
Do I need the sink and tap before the worktop is cut?
You need at least the exact sink and tap models and their templates. An undermount or flush sink needs fabrication on the slab, and the tap needs drilled holes of the right diameter. The physical products can arrive later, but the data must be final before cutting.
How do I avoid forgetting small fittings?
Make them separate estimate items grouped by supplier and delivery. Go through each appliance and each cabinet and ask what connects it: valve, hose, siphon, socket, handle, hinge, sealant. Review the list with the kitchen maker and the plumber before the last order is placed.
Should I order appliances before the renovation starts?
Specify them before, but delivery can wait until the cabinets are close to installation. Early delivery means storage, risk of damage and warranty periods that start too soon. If the lead time is long, order early and agree storage with the supplier or on site.
What do I check when appliances arrive on site?
Compare the SKU, colour, dimensions and quantity with the estimate, and look for transport damage before signing. Photograph the labels and any defects. Record the result per item, so that a discrepancy claim to the supplier has a clear comment and photos behind it.